50 Percent of Kennedy

Huntington Ingalls Industries’ (HII) Newport News Shipbuilding division reached the midpoint in the construction of the nuclear-powered aircraft carrier USS John F. Kennedy (CVN-79) following the installation of one of the largest units on the ship.

USS John F. Kennedy (CVN-79) Aft Section Superlift
USS John F. Kennedy (CVN-79) Aft Section Superlift

Weighing approximately 905 metric tons, the unit is one of the heaviest of the planned steel structures, known as superlifts, that will be joined together to make up the second ship in the Gerald R. Ford class. The superlift of the aft section of the ship between the hangar bay and flight deck is 80 feet/24.4 m long, about 110 feet/33.5 m wide and four decks in height.

Combining 19 smaller units into one superlift allowed Newport News to install a majority of the outfitting equipment – grating, pumps, valves, pipe, electrical panels, mounting studs, lighting, ventilation and other components – before the structure was hoisted into the dry dock using the shipyard’s 1,050-metric ton gantry crane. This approach resulted in this work being completed 14 months earlier than it was on Ford, said Lucas Hicks, Newport News’ vice president, CVN-79 program.

«This was a game changer for us», Hicks said. «Performing higher levels of pre-outfitting represents a significant improvement in aircraft carrier construction, allowing us to build larger structures than ever before and providing greater cost savings».

«This superlift represents the future build strategy for Ford-class carriers», said Mike Butler, program director of CVN-79. «Not only did we build this superlift larger and with significantly more pre-outfitting, we managed much of the work on the deckplate with new digital project management tools as part of our Integrated Digital Shipbuilding initiative. The lessons we learned from this successful superlift will allow us to build even more similar superlifts on future ships in the Ford class».

Kennedy is scheduled to move from the dry dock to an outfitting berth in the fourth quarter of 2019, three months ahead of schedule.

 

General Characteristics

Builder Huntington Ingalls Industries Newport News Shipbuilding, Newport News, Virginia
Propulsion 2 A1B* nuclear reactors, 4 shafts
Length 1,092 feet/333 m
Beam 134 feet/41 m
Flight Deck Width 256 feet/78 m
Flight Deck Square 217,796 feet2/20,234 m2
Displacement approximately 100,000 long tons full load
Speed 30+ knots/34.5+ mph/55.5+ km/h
Crew 4,539 (ship, air wing and staff)
Armament ESSM (Evolved Sea Sparrow Missile), RAM (Rolling Airframe Missile), Mk-15 Phalanx CIWS (Close-In Weapon System)
Aircraft 75+

* – Bechtel Plant Machinery, Inc. serves the U.S. Naval Nuclear Propulsion Program

 

Ships

Ship Laid down Launched Commissioned Homeport
USS Gerald R. Ford (CVN-78) 11-13-2009 11-09-2013 07-22-2017 Norfolk, Virginia
USS John F. Kennedy (CVN-79) 08-22-2015
USS Enterprise (CVN-80)